Chesterfield Baker Tareyton
In 2021, infrastructure upgrades were undertaken on Chesterfield Drive, Tareyton Road, and Bakers Lane. The work included full replacement of sanitary sewers, watermains and associated structures, and road works including road base improvements and a new asphalt surface. Existing ditches were cleaned out, reinstating proper ditching on each side of the road, and driveway culverts replaced.
For further information please contact:
Joe Gratton
Project Supervisor
613-386-7351 Ext. 172
Email Joe Gratton
Current Project Update:
October 20, 2023: The Township has accepted the work done with respect to sod placement, and the landscaper contractor's responsibilities are complete. The responsibility of watering and caring for the new sod now passes to individual property owners. A letter confirming this is being delivered to affected residents today.
Past Project Updates:
September 28, 2023: Staff have done a walk-through of the project area with the landscape contractor. The Township has not yet assumed the landscaping as complete, and the contractor continues to maintain the area.
August 18, 2023: Sod installations were completed on August 3, 2023. The contractor is responsible for watering and maintaining the sod for 30 days following installation. Township staff are monitoring the area during this time and will inspect at the 30-day period.
July 24, 2023: Sod installations are expected to be completed by the end of July. A letter regarding sod care is being hand-delivered today to all addresses where sod replacement was requested. The contractor is responsible for watering and maintaining the sod for 30 days following installation.
June 22, 2023: No additional requests for sod replacement will be accepted after June 29, 2023. A letter confirming this is being hand-delivered to all residents in the project area today.
June 20, 2023: The planned sod replacement has been delayed by several weeks as additional locations are added to the scope. Each additional location requires that underground infrastructure locates be obtained before the contractor can strip the existing turf.
May 29, 2023 - Sod replacement will begin on June 5, 2023.
May 16, 2023 - Driveway replacement is now complete in the project area. Sod replacement will be complete before mid-June.
May 5, 2023 - Sod and driveway replacement is scheduled to take place in the next several weeks. A letter has been hand-delivered today to residents in the project area providing more details.
January 6, 2023 - A letter was hand-delivered regarding sod and driveway replacements to be undertaken in spring 2023.
October 28, 2022 - A letter was hand-delivered addressing residents' concerns.
October 6, 2022 - A letter was hand-delivered to residents in the project area. Staff will be in contact with residents again in early November to discuss individual resident concerns, in preparation for the subsequent staff report that will be presented to the new Council.
August 23, 2022 - Township staff held a Public Information Centre at the Amherstview Community Hall to hear resident concerns regarding the project restoration undertaken to date. Following that, a staff report was received by Council at their regular session on September 12, 2022. Subsequently, Loyalist Township Council passed Resolution 2022.71.16:
"Moved by Councillor Gordon and Seconded by Councillor Townend that the report from the Engineering and Environment Division, September 12, 2022 re: Chesterfield-Bakers-Tareyton Restoration Update, be received; and
That Council direct staff to report back to Council after new Council inauguration to propose funding plan and obtain approval to move forward with replacing seeded areas with sod for any resident who requests it and reimburse those residents who have paid to put down sod on their own; and further, that the Township repair any cosmetic tire marks on the new pavement caused by issues beyond our control and that such cost be taken from budget; and that the Township still hold the contractors for outstanding deficiencies."
April 2022 - Township staff conducted a walk-through of the project site with the contractor to identify outstanding work.
July 2021 - The work began in late July 2021 and the contractor continued until winter shutdown.