Date | Description |
June 2017 |
|
July 2018 |
- Loyalist Township retains the services of MacLennan Jaunkalns Miller Architects (MJMA) to undertake a Feasibility Study for the development of a Sustainable Community Hub.
|
Q1 2021 |
|
June 2021 |
- Council approves funding to advance the schematic design of the proposed facility.
|
July 2021 |
- Funding application submitted to the Green and Inclusive Community Building Fund.
|
March 2022 |
- Failure of pool infrastructure at the W.J. Henderson Recreation Centre.
|
April 2022 |
- Pool closed at the direction of Council based on the result of a structural assessment of the pool basin.
|
July 2022 |
- $670,000 in funding approved from the Renewable Energy Benefit Fund ($167,500 from Ward 1 and $502,500 from Ward 2/3)
|
July 2022 |
|
December 2022 |
|
January 2023 |
- Public consultation to refine the proposed design and inform future programming for the facility.
|
Summer 2023 |
- Develop Validation Report and funding plan for the construction phase of the project.
|
August 2023 |
- Presentation of Validation Report and funding plan to Council for approval.
|