Odessa West Drainage & Road Improvements Project
Loyalist Township is making infrastructure upgrades in Odessa West, including Battery Street, Emma Street, Cross Street, South Street, and Bridge Street. A copy of the design drawings is posted below, along with other project-related information and updates. The multi-year construction project started in early summer 2023, and will conclude in 2024. Remember to sign up to receive project update emails!
Although this work may cause temporary disruptions as it will require excavation of the road, ditches, and driveway culverts, access to individual properties will be maintained throughout the project. Once completed, these upgrades are expected to result in:
- Reduced service interruptions;
- Improved right-of-way drainage;
- A preserved road base and longer-lasting asphalt surface;
- Upgraded water infrastructure for better reliability in the future.
Current Project Update:
March 28, 2024: The Township's contractor, K. Mulrooney Trucking, is preparing to continue the watermain, road, and storm sewer reconstruction. 2024's construction season will begin with the section of Bridge Street between Emma and Main, and households in this section will be transitioned to temporary water as soon as temperatures allow. Additional information regarding temporary water will be provided to residents as needed in your location.
As the project progresses, traffic detours will be necessary and will shift gradually to accommodate work locations. The contractor will be instructed to maintain access to all driveways; however, circumstances may cause temporary access restrictions. If this is to occur, the contractor will contact affected residents individually to plan for any closures and make every attempt to accommodate special circumstances.
Remember to sign up for the project email list to get email updates. If you have concerns please contact the Project Supervisor, Joe Gratton by email or by phone at 613-386-7351, ext. 172#.
Past project updates |
November 15, 2023: As the relocation of utility poles on Emma Street has been completed, the contractor has remobilized onsite and is continuing work on Emma. The work will continue as long as weather conditions allow, after which the contractor will shut down until 2024. As the weather turns cooler, construction will generally continue as long as weather conditions allow. We will remain in contact with residents throughout the fall months as the project progresses. September 28, 2023: Since construction began at the south end of Bridge Street earlier this summer, the contractor has placed new storm sewers and watermain along Bridge Street north of Emma, and is currently working on the realignment of Emma Street, including placing watermain, storm and sanitary sewers, and coordinating with Bell, Hydro One, and Enbridge for the relocation of service poles, wires, and gas mains. Shortly the contractor will start hydroseeding disturbed grassy areas and reinstating driveways. We will provide hydroseed and asphalt care information to affected residents. June 23, 2023: Township staff and the contractor are preparing for construction to get underway. Construction is expected to begin the first week of July. Residents and neighbourhood visitors may notice preliminary activity during the week of June 26. A notice with this information has been hand-delivered to all residents in the project area. June 6, 2023: Project staff are currently finalizing contract details with the contractor. Residents in the affected area may soon start to see evidence of underground infrastructure locates and equipment and machinery on site, as well as concurrent work being undertaken by Enbridge Gas. May 24, 2023: At their regular session on May 23, Loyalist Township Council awarded the contract for this project to K. Mulrooney Trucking Limited. More details on project mobilization and start date will follow in the coming weeks. May 5, 2023: Malroz Engineering will be drilling boreholes in the road right-of-way in the project area. The work will start the week of May 8 and will provide geotechnical information to support the project design. April 16, 2023 - Draft construction drawings were added to the project website. The drawings can be viewed below. March 28, 2023 - A virtual information session for the community was held on Tuesday, March 28, 2023. A recording of the session has been uploaded to the project page. March 13, 2023 – A project letter was hand-delivered to residents in the project area. Providing information about the project and promoting the virtual information session. |
Odessa West, Water, Storm Water, Drainage & Road Improvements Project Public Information Webinar:
A virtual public information session was held on Tuesday, March 28, 2022, at 6 p.m. Staff were on hand to present the design drawings, receive feedback, and answer questions on the project. The session was recorded for those who were unable to attend and transcribed.
Click the thumbnail below to watch the full webinar recording.
Draft Construction Drawings:
A draft design has been prepared at this project stage and is available for review below.
Odessa West Drainage Improvement Project Draft Drawings (PDF)
Providing Feedback:
Township staff can meet at your residence or virtually to discuss any questions you have about the project. In addition, don't hesitate to contact the Project Supervisor at the phone number or e-mail below to set up an appointment or discuss any other questions or concerns.
Joe Gratton, Project Supervisor - 613-386-7351, ext. 172#
Sign up to receive project-specific email updates:
Stay updated on the Odessa West Water, Storm Water, Drainage & Road Improvements project by signing up for the project email list.
Contact Us